Comprehensive engineering preparation of the territory

If you need a project of complex engineering preparation of the territory for construction - we are ready to offer optimal technical solutions using the most modern equipment (both imported and domestically produced) on the basis of a technical and economic comparison of options that allow the realization of the customer's investment plan.

Our experience in the field of designing engineering infrastructure objects and a comprehensive approach allows us to offer a competitive price and provide a guaranteed result. We perform a full range of work from the collection of initial data, approvals and expertise to the author's supervision and commissioning.

Procedure for engineering preparation of territories

Company "Gutman Construction"

The basis of engineering preparation of territories should be:

  1. Concept of implementation of the investment project and stages of its development.
  2. Rules included in the Urban Planning Code of Ukraine.
  3. Building norms and rules (SNiPy).


Any construction begins with engineering preparation of the territory:

  • construction of roads
  • laying of water pipes and drainage (sewage)
  • laying cable networks
  • gas pipelines
  • treatment plant
  • water intakes
  • water treatment stations and pumping stations
  • etc.

That is why the correct organization and technologies of carrying out these and other works related to preparatory works are so important.

It should be noted that both from an organizational and technical point of view, the engineering preparation of territories for development has always been considered and is considered the most difficult and time-consuming process.

The fact is that the engineering preparation of territories — especially in the case of complex development of districts of quarters for the future construction of objects — requires particularly clear, coordinated in time and space actions of all participants of such work. After all, engineering networks are closely technologically interconnected.

Even more important is a well-thought-out plan of action in the engineering preparation of large areas, unfortunately, it should be noted that in many cases there is no such consistency.

Stages of engineering training

Company "Gutman Construction"

  • Territory planning project (which must have an engineering component)
  • Collection of raw data and development of the engineering training project
  • Construction and development of "main" infrastructure facilities
  • Construction of main engineering communications
  • Engineering preparation of building blocks
  • Intra-quarter engineering training
  • Bringing engineering networks to specific objects

Changing terrain

Company "Gutman Construction"

At the design stage of engineering preparation, it is necessary to ensure the creation of a relief under directive marks dictated by the position of the existing road network, drainage or, on the contrary, washing of territories, replacement of contaminated soil, performance of complex hydraulic calculations of networks within the planned pre-development area. All this should be done at the stage of development of the project of planning and demarcation of the territory and working design.

Coordination problems

Company "Gutman Construction"

Even with perfect compliance with all stages of the problem, there are numerous contractors whose coordination practically does not occur, although it would be logical to entrust such coordination to the General Designer.

The main inconsistency arises at the level of Designing engineering preparation of territories, because some of them are occupied only by cable networks, others by water pipes, others by gas, etc. There are very few qualified companies on the market of design organizations that are ready to organize and coordinate the entire complex of project works on engineering preparation of the territory, taking into account the phasing of the implementation of the customer's investment project.

The lack of experience in the implementation of infrastructure projects leads to the adoption of non-rational decisions (acceptable from the point of view of SNiP, etc.), which can limit the possibilities of development and expansion of engineering capacities or significantly increase operating costs, etc.

Failure to properly connect project solutions and actions of individual customers and their contractors during the connection of networks to individual construction sites lead to a significant increase in the price of construction and installation works and disruption of deadlines.

To eliminate these inconsistencies, a single general designer for engineering preparation of the territory should be determined, taking into account the experience of implementing such projects.

Even bigger problems arise during the so-called renovation of already built-up areas, in particular, there it is necessary to reconstruct all engineering communications in a comprehensive and coordinated manner without disrupting the functionality of the main trunk networks.

Offer

Company "Gutman Construction"

Specialists of Company "Gutman Construction" have considerable experience not only in designing, but also in author supervision of the implementation of such objects. We guarantee that during the implementation of your investment project, based on a technical and economic comparison of options, we will make optimal decisions with the use of modern energy-efficient technologies and taking into account the phased commissioning of the facility, which in turn will allow the most efficient distribution of capital investments and ensure the return of investments in the shortest possible time.

As part of the development of a feasibility study for the engineering preparation of the territory, our company performs a comprehensive analysis of this engineering and investment task.

The process of developing a feasibility study

is divided into 7 stages

  • 1st stage. Analysis of European experience.
  • 2nd stage. Collection and analysis of raw data.
  • 3rd stage. A detailed engineering and technical review of the options, separately for each system for each element (object) of the scheme with a detailed review of the main technical factors affecting the main and operational costs. Discrete techno-economic comparison of options. Modeling according to variants of system schemes.
  • 4th stage. General scheme of engineering training. Based on the materials of the considered options, matrix models of the considered options are made. Matrix analysis will allow finding optimal balance ratios of costs and results of production and economic activity. Optimization of the schemes obtained at the previous stages of the feasibility study development.
  • 5th stage. Final modeling. Modeling of variants of the general scheme of engineering training on the basis of optimal solutions obtained at the previous stages of feasibility study development.
    Modeling and mathematical analysis of the entire system.
  • 6th stage. Development of variants of the general system of monitoring, accounting and management of systems.
  • 7th stage. Results of technical and economic comparison. Conclusions.
Based on a comprehensive analysis of the raw data

projects of technical tasks are being prepared

  1. Terms of reference for complex engineering studies (including organization of water intake and release of treated wastewater).
  2. Terms of reference for comprehensive landscaping outside the quarter territories of the district according to the project "Engineering support of the land plot. For its development for the purpose of building".
  3. Technical task of designing engineering systems for external lighting of roads, external power supply from TP to sites.
  4. Technical task for the design of engineering systems: telephone communication, LOM, broadcast television, security television, security and fire alarm, notification and management of evacuation during a fire, radiofication with connection to RASTC, access control and management (ACS).
  5. The technical task of designing engineering systems: heat supply, in particular of a gas boiler room.
  6. Terms of reference for the design of engineering systems: water supply, drainage and storm sewerage.
    Terms of reference for building inspection works.
  7. From the approved technical tasks and according to the materials of the feasibility study, the design and estimate documentation of the P and R stage is being developed.
  8. All decisions made in the design process are protected by Company "Gutman Construction" specialists in the process of approvals and during the examination of design documentation.
exposure

MAIN DIFFICULTIES AND ERRORS

during design preparation

The main difficulties and mistakes
with independent design:

  1. Lack of an agreed project of the Sanitary Protection Zone (SZZ)
  2. Lack of metering devices and objective (calculated) data on the required productivity.
  3. Lack of title deeds to the land.
  4. Inaccuracies in the preparation of the Terms of Reference: all the necessary studies were not taken into account, the documents listed above were not taken into account.
  5. The justification of the price was performed incorrectly, on the basis of commercial proposals of non-specialized organizations, without taking into account the fulfillment of the requirements of technical conditions, the need for inspection of buildings and structures, etc.
  6. Surveys, research, and design are performed by different companies, which causes delays and additional work.

 Decisions from
Company "Gutman Construction":

  • We will analyze the existing situation, prepare the Terms of Reference for the SZZ project. If necessary, we will execute the project of SZZ and agree on it.
  • We will collect all the necessary data, make calculations and submit it to the customer for consideration. If necessary, we will temporarily install metering devices.
  • We will help in the preparation of documentation, if necessary, we will include it in the TOR for design.
  • We will analyze the existing situation and prepare the correct technical task.
  • We will prepare an estimate for design and exploration works and surveys, based on basic price guides.
  • We have considerable experience and qualifications for the organization of a full range of design and search works. Company "Gutman Construction" has SRO permits for both design and exploration work. We are guaranteed to provide a positive conclusion of the examination and support during SMR.

The cost of project development

The best offer from Company "Gutman Construction"

Company "Gutman Construction" uses a time-tested method to determine the basic (initial) cost of design and estimate documentation and exploration works: drawing up an estimate for the PVR according to the basic price guides. The estimated cost of design and research works is a justified initial cost of works, which is specified in the process of clarifying the scope of works and negotiations. The cost estimate for the PVR drawn up according to the basic price guides can be the justification of the price during the tender procedure in accordance with the legislation.

Also, we facilitate the attraction of credit funds for the implementation of energy service contracts (energy efficiency) and environmental projects.

rocket_launch

By starting cooperation with us You save:

Costs
on construction and assembly works
Based on variant design and modern technologies, we select the optimal solution. 3D modeling technologies help to avoid overspending of materials and minimize the possibility of mistakes.

Costs of design and research worksAt the same time, you get a high-quality project that allows you to realize your idea on time. Thanks to the comprehensive approach, all in one hand (collection of initial data, survey and measurements, research) and the experience of our specialists, we can optimize costs and offer you a competitive price.

Time during construction and assembly worksThe solutions adopted by our engineers and architects are not only reliable and aesthetic, but also thought out from the point of view of convenience and speed of implementation (flexible solutions from the point of view of execution of works).

⚠️ . As part of the design contract, we always prescribe warranty obligations and material liability for failure of deadlines.

We will prepare all technical tasks

architecturebookmark_added

For designing

engineeringdesign_services

For inspection

pending_actionsworkspace_premium

For research

view_in_arwork_outline

To develop a scheme

Specialists of Company "Gutman Construction" are ready to help at all stages of decision-making, both at the stage of considering the project concept and when considering options for the reconstruction of existing buildings and structures. At the stage of design preparation, prepare technical tasks for design and the necessary searches. And also to prepare estimates for design and research based on basic price collections (justification of the price for the competition).

How do we design?

filter_1settings_accessibility

The customer's idea

filter_2foundation

Preparation of pre-project solutions and design options

filter_3query_stats

Development of a technical and economic feasibility study (FES)

filter_4admin_panel_settings

Protection of basic decisions before the customer, selection of the best option

filter_5rebase_edit

Preparation of detailed specifications for project development, engineering studies, survey

filter_6auto_stories

Project development - stage "P"

filter_7published_with_changes

Examination of design and estimate documentation

filter_8offline_pin

Development of working documentation and approval

filter_9engineering

Author supervision

Everything is ready! 😀 The customer's idea has been realized!